You must prepare, keep, comply with and review a safe work method statement for high risk construction work.

 To be able to carry out construction work, a person must complete an introductory safety training course called ‘general construction induction training’. This is also commonly known as ‘white card’ training.

High risk construction work:

  • involves a risk of a person falling more than 2 m
  • is carried out on a telecommunication tower
  • involves demolition of an element of a structure that is load-bearing
  • involves demolition of an element of a structure that is related to the physical integrity of the structure
  • involves, or is likely to involve, disturbing asbestos
  • involves structural alteration or repair that requires temporary support to prevent collapse
  • is carried out in or near a confined space
  • is carried out in or near a shaft or trench deeper than 1.5 m or a tunnel
  • involves the use of explosives
  • is carried out on or near pressurised gas mains or piping
  • is carried out on or near chemical, fuel or refrigerant lines
  • is carried out on or near energised electrical installations or services
  • is carried out in an area that may have a contaminated or flammable atmosphere
  • involves tilt-up or precast concrete
  • is carried out on, in or adjacent to a road, railway, shipping lane or other traffic corridor in use by traffic other than pedestrians
  • is carried out in an area of a workplace where there is any movement of powered mobile plant
  • is carried out in areas with artificial extremes of temperature
  • is carried out in or near water or other liquid that involves a risk of drowning
  • involves diving work